Finishing the house

Every time I come to Holland, to this unfinished house, I start longing to return to my own finished house in London. I close my eyes and wave my hands, as if by magic, the house would become finished and liveable. That is perhaps one of the reasons why I haven't moved here completely.

Enough wishful thinking. Although I'm pretty hopeless at building work, I have managed projects before. One of my former employers had sent me on a three-day professional project management course, and I still remember the key lessons.

One is to identify the critical path - what has to be done. Another is to set the milestones. Finally, it's important to build slack.

Finishing this house is absolutely vital for my own sanity. So I will apply those project management skills now --- starting with the following list.

Area Work Effort Priority/Importance
Front of the house
Plaster outside wall
Hire professional
Low - weather dependent
 
Paint outside wall
1 day
Low - weather dependent
 
Change door knob
0.5 hour
Low - pleasing to eye
 
Change mail box cover
0.5 hour
Low - pleasing to eye
 
Fix doorbell
1 hour
Low
Hallway
Plaster & paint wall adjacent to neighbours
1.5 days
Low - pleasing to eye
 
Fix gyps board to walls upstairs, paint over
1.5 days
Low - pleasing to eye
 
Paint stairs or sand down to expose original wood
several days
Last - to dry when Anne is away
 
Get doormat
1 hour
High - to keep the house clean
Living / dining room
Sand down and paint insulated wall
1 hour
High - to finish the living room and to make way for shelves
 
Measure, cut, fix in skirting board
0.5 hour
High - to finish the living room and to make way for shelves
 
Measure, buy, put up new shelves
1 day
High - to finish the living room and to make way for shelves
 
Paint pipes and close holes
 
Low
Kitchen
Plaster and paint wall
Hire professional
Med - to finish kitchen
 
Fix skirting boards
1 hour
Med - to finish kitchen
 
Measure, select, buy, fit, blue tiles
1 day
Med - to finish kitchen
 
Build cabinet around the boiler
0.5 day
Med - to finish kitchen & prevent draft
 
Build shelves next to boiler cabinet
 
Med - to finish kitchen and make extra storage space
 
Build window sill above radiator
 
Med - to finish kitchen
 
Replace door lock
 
Low
Bathroom
Fix leak in toilet
 
High
 
Diagnose and fix lack of hot water in shower
 
High
 
Remove old tiles around bathtub and sink
 
High
 
Make wall around bathtub
 
High
 
Fill holes, cracks, remove cement spills
 
High
 
Fix new tiles
 
High
 
Make cabinet above sink mirror
 
Low
 
Install floor heating
 
Low
 
Get outside fan
 
Low
 
Add natural light - window
 
Low
 
Replace door panels with glass
 
Low
Front study
Add curtain rail
 
Low
 
Buy & fix curtains
 
Low
 
Lower desk
 
High
Back study
Knock out inner wall & insulate
3 hours
High
 
Paint walls
 
High
 
Make desk
 
High
 
Make shelf space
 
High
 
Make closet
 
High
 
Replace curtains
 
Low
Bedroom
Finish paintwork
 
Low
 
Replace curtains
 
Low
 
Paint ceiling
 
Low
Attic
Finish front section
 
Low
 
Make shelves
 
Low
 
Finish insulation
 
Low
Upstairs patio
Get rid of screen door
easy
Low
 
Paint outside wall
 
Low - weather dependent
Shed
Knock out and replace entirely
 
Last - low
Garden
Paint garden door
 
Last - low - weather dependent

Next, I will act as project manager, or rather, quartermaster, to make sure the project is delivered on time and within budget.

9 January 2004 Friday

London house to let
Like this entry?
Your comments:
Your email address:
Tell your friends about this Bon Journal entry:
Your name:
Your email address:
Your friend(s):
 (please separate additional addresses with commas)
Your message:

Anne Ku at Ilp in May 2001
Anne Ku

writes about her travels, conversations, thoughts, events, music, and anything else that is interesting enough to fill a web page.
Support the Bon Journal by keeping analyticalQ.com alive and free. Find out about Sponsorship.