Finishing the house
Every time I come to Holland, to this unfinished house, I start longing
to return to my own finished house in London. I close my eyes and wave
my hands, as if by magic, the house would become finished and liveable.
That is perhaps one of the reasons why I haven't moved here completely.
Enough wishful thinking. Although I'm pretty hopeless at building work,
I have managed projects before. One of my former employers had sent me
on a three-day professional project management course, and I still remember
the key lessons.
One is to identify the critical path - what has to be done. Another is
to set the milestones. Finally, it's important to build slack.
Finishing this house is absolutely vital for my own sanity. So I will
apply those project management skills now --- starting with the following
list.
Area |
Work |
Effort |
Priority/Importance |
Front of the house
|
Plaster outside wall
|
Hire professional
|
Low - weather dependent
|
|
Paint outside wall
|
1 day
|
Low - weather dependent
|
|
Change door knob
|
0.5 hour
|
Low - pleasing to eye
|
|
Change mail box cover
|
0.5 hour
|
Low - pleasing to eye
|
|
Fix doorbell
|
1 hour
|
Low
|
Hallway
|
Plaster & paint wall adjacent to neighbours
|
1.5 days
|
Low - pleasing to eye
|
|
Fix gyps board to walls upstairs, paint over
|
1.5 days
|
Low - pleasing to eye
|
|
Paint stairs or sand down to expose original wood
|
several days
|
Last - to dry when Anne is away
|
|
Get doormat
|
1 hour
|
High - to keep the house clean
|
Living / dining room
|
Sand down and paint insulated wall
|
1 hour
|
High - to finish the living room and to make way for shelves
|
|
Measure, cut, fix in skirting board
|
0.5 hour
|
High - to finish the living room and to make way for shelves
|
|
Measure, buy, put up new shelves
|
1 day
|
High - to finish the living room and to make way for shelves
|
|
Paint pipes and close holes
|
|
Low
|
Kitchen
|
Plaster and paint wall
|
Hire professional
|
Med - to finish kitchen
|
|
Fix skirting boards
|
1 hour
|
Med - to finish kitchen
|
|
Measure, select, buy, fit, blue tiles
|
1 day
|
Med - to finish kitchen
|
|
Build cabinet around the boiler
|
0.5 day
|
Med - to finish kitchen & prevent draft
|
|
Build shelves next to boiler cabinet
|
|
Med - to finish kitchen and make extra storage space
|
|
Build window sill above radiator
|
|
Med - to finish kitchen
|
|
Replace door lock
|
|
Low
|
Bathroom
|
Fix leak in toilet
|
|
High
|
|
Diagnose and fix lack of hot water in shower
|
|
High
|
|
Remove old tiles around bathtub and sink
|
|
High
|
|
Make wall around bathtub
|
|
High
|
|
Fill holes, cracks, remove cement spills
|
|
High
|
|
Fix new tiles
|
|
High
|
|
Make cabinet above sink mirror
|
|
Low
|
|
Install floor heating
|
|
Low
|
|
Get outside fan
|
|
Low
|
|
Add natural light - window
|
|
Low
|
|
Replace door panels with glass
|
|
Low
|
Front study
|
Add curtain rail
|
|
Low
|
|
Buy & fix curtains
|
|
Low
|
|
Lower desk
|
|
High
|
Back study
|
Knock out inner wall & insulate
|
3 hours
|
High
|
|
Paint walls
|
|
High
|
|
Make desk
|
|
High
|
|
Make shelf space
|
|
High
|
|
Make closet
|
|
High
|
|
Replace curtains
|
|
Low
|
Bedroom
|
Finish paintwork
|
|
Low
|
|
Replace curtains
|
|
Low
|
|
Paint ceiling
|
|
Low
|
Attic
|
Finish front section
|
|
Low
|
|
Make shelves
|
|
Low
|
|
Finish insulation
|
|
Low
|
Upstairs patio
|
Get rid of screen door
|
easy
|
Low
|
|
Paint outside wall
|
|
Low - weather dependent
|
Shed
|
Knock out and replace entirely
|
|
Last - low
|
Garden
|
Paint garden door
|
|
Last - low - weather dependent
|
Next, I will act as project manager, or rather, quartermaster, to make
sure the project is delivered on time and within budget.
9 January 2004 Friday
|
|
|
Tell your friends about this Bon
Journal entry:
|
|
Anne Ku writes
about her travels, conversations, thoughts, events, music, and anything else that
is interesting enough to fill a web page.
Support the Bon Journal by keeping analyticalQ.com alive and free.
Find out about Sponsorship. |
|